July 2018

Since last month, Valenti-Held Contractor/Developer has landed two new projects: Osbourne Trails Section 1 (Platinum Properties) and Enclave at Andover Section 3 (Pulte Homes). Osbourne Trails Section 1 will likely begin the first part of July and Enclave at Andover Section 3 will start shortly thereafter.

Osbourne Trails Section 1 – Westfield, IN – Platinum Properties:
+166,000CY’s of earthwork
+107 Utility days – 3,751’ of sanitary sewer, 6,274’ of storm sewer and 7,481’ of 8-16” water main.

Enclave at Andover Section 3– Westfield, IN – Pulte Homes:
+5,774CY’s of earthwork
+16.3 Utility days – 985’ of sanitary sewer, 195’ of storm sewer and 1,320’ of water main.

Valenti-Held is still receiving bids, and the focus has turned to fall dirt and winter utility projects and any work that would start in 2019. As things stand, we only have a few spots left for new projects this year. We also should be getting the “official” word on at least 2-5 projects in the month of July.

This entry was posted in Uncategorized. Bookmark the permalink. Follow any comments here with the RSS feed for this post. Both comments and trackbacks are currently closed.