Since last month, Valenti-Held Contractor/Developer has landed two new projects: Harmony Section 5 (Westfield) and Center Street (Whitestown). These projects will start this month on top of the projects mentioned in last month’s article. Harmony Section 5 is a continuation of the previous four sections that Valenti-Held has done for Estridge, and this section is at the southwest corner of 156th Street and Ditch Road in Westfield. There is approximately 104,000CY’s of dirt and 121 days of utility work. Center Street is a roadway project at Whitestown Crossing that will need to be paved this year. The earthwork for the roadway is mostly complete. The utilities will start within the next two weeks, and there is approximately 29 days of utility work.